Grade Separation Work Update

Caltrain Construction and Maintenance: Dec. 8 to Dec. 14, 2012

Construction

San Bruno Grade Separation Project

Work on the grade separation project continues with utilities work and a temporary detour. There will be a temporary detour of the right-turning traffic on Northbound Huntington Avenue to Northbound San Mateo Avenue. The detour will be in effect from Monday, Dec. 10, until Friday, Dec. 14, 7:00 a.m. until 3:30 p.m.

Motorists heading Northbound on Huntington to San Mateo Avenue will be able to take a right turn onto San Bruno Avenue, turn left onto 2nd Avenue, and turn left on Walnut Street.

Day work, which includes digging with a backhoe and mini-excavator, will be done from 7 a.m. to 4 p.m. Crews will excavate, install utility infrastructure, place concrete panels using a crane, and pour concrete. Crews will use medium and heavy duty diesel vehicles to transport dirt and concrete.

Night work will occur from Sunday, Dec. 9, through Friday, Dec. 14, between 11 p.m. and 7 a.m. Crews will pour concrete and use a crane to place concrete panels.

The $147 million project will elevate the Caltrain tracks above three existing at-grade street crossings at San Bruno, San Mateo and Angus Avenues.  A new elevated Caltrain station between San Bruno and San Mateo Avenues will replace the station at Sylvan Avenue. Work on this project will not disrupt Caltrain service.

For more information, please call the dedicated outreach line at 650.508.7726 or email sbgradesep@caltrain.com.

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something
See more »